The Ethiopian Electric Power has announced that it is unable to supply enough power to companies engaged in data mining.
As a result, there is a gap between the plan and the implementation in the fiscal year, the institute said.
In the fiscal year, it was planned to earn 27.71 million dollars by providing 882.48 million gigawatt hours of power to the companies engaged in data mining.
However, it is said that 796.28 million gigawatt-hours of electricity was generated, generating more than $25 million in revenue.
We have seen from the institution's social network page that it has achieved more than 90 percent of the plan.
by Biruktawit Asrat
2024-08-28