It has been announced that the Dire Dawa Shenle road construction project has been postponed.

It has been announced that the Dire Dawa Shenle road construction project has been postponed.

Back in 2012. It has been reported that the Dire Dawa Shenle road construction project has not been completed within the planned time limit.

Standing Committee for Urban Infrastructure and Transport Affairs has announced that the road construction is 53 percent completed.

It has been stated that the existence of electricity infrastructure that has not been paid more than 750 million birrs in compensation, the problem of fuel and cement supply is the reason for the delay of the project.

The construction of the road in 2017. House of Representatives has announced on his social media that the project supervisor engineer said when it will be completed.

by Mulugeta Belay
2024-01-16